100R-19Beginner18 min readFeatured

Contract Change Management (EPC)

A beginner's guide to contract change management — spot a change, give notice, price it, and authorise it before the work is done, so a routine change order never becomes a dispute. Built on AACE 100R-19.

What exactly is a "change"?

When a contract is signed, three things are fixed: the scope (what will be built), the time (by when), and the price (for how much). Together they form the contract baseline — the promise both parties made.

CONTRACT BASELINEAgreed scope · time · price+ Change (Δ)REVISED BASELINE (after authorized change order)New scope · new time · new price — agreed by both parties
A change shifts the baseline — deliberately, on paper. The contract baseline plus an authorized change order equals a revised baseline both parties agree to.

Two doors: directed and constructive

Change enters a project through one of two doors. The first is obvious; the second is the one that sinks projects. Telling them apart is the most important distinction in this lesson.

Directed changeConstructive change
How it happensFormally instructed in writing — a change order, field directive, or variationThe contractor is effectively forced beyond the contract, with no formal order
Typical causeThe owner decides to add or alter scopeDefective design, over-inspection, denied access, a disputed interpretation
Is a change obvious?Yes — everyone agrees a change occurredNo — the change is real but the paperwork is missing
Where it ends upA priced, agreed change orderA claim — argued later, with the burden on the contractor

A rarer beast is the cardinal change — a change so large or fundamental that it falls outside the contract's "changes" clause entirely, effectively a new contract. Most changes are nowhere near cardinal; they're incremental adjustments handled through the change-order process.

The change-order lifecycle

A well-run project turns every potential change into an authorised change order through the same six steps. Skipping one is where money and time leak away.

  1. Identify — recognise a deviation from scope, time, or price and log it the moment it appears, before any work proceeds.
  2. Notice — notify the other party in writing within the contract's time limit; this preserves the right to claim and lets the owner mitigate.
  3. Price & time — quantify the added cost and any schedule impact: build the cost bottom-up, model the time as a fragnet.
  4. Negotiate — agree the scope, value, and any extension of time, supporting every number with verifiable backup.
  5. Authorise — both parties sign the change order before the work is done.
  6. Incorporate — update the budget and schedule baselines and track the change to closeout.

Notice: the clause that can win or lose entitlement

Almost every construction contract requires the contractor to give notice of a change within a fixed number of days — often 7, 14, or 28. Notice isn't bureaucracy: it lets the owner mitigate, inspect conditions before they're covered up, and make an informed decision. Miss the window, and a contractually valid change can be barred purely on a timeliness defence — the money was owed, but the right to claim it expired.

EVENTChange occursNotice window (e.g. 14 days)Give notice ✓Notice here may be time-barred ✗
The notice window. Give notice inside the contractual window; after it, even a valid change can be time-barred.

Worked example — building up a change-order price

A change-order price is built from the bottom up: direct costs first, then the markups the contract allows. The owner directs the contractor to install 12 additional equipment foundations not in the original scope. Here's the build-up.

From direct cost to change-order value

Worked example
Cost elementBasisAmount (USD)
Direct labour480 hr × $45.0021,600
Materialtakeoff14,000
Equipmentrental + operating6,400
Subcontracted workquote8,000
Direct cost subtotal50,000
Field / site overhead12% of 50,0006,000
Home-office overhead8% of 56,0004,480
Profit10% of 60,4806,048
Bond & insurance1.5% of 66,528998
CHANGE ORDER VALUE — direct $50,000 built up through compounding markups= 67,526

The markups compound — each tier applies to the running subtotal, so the order they stack in matters and must follow the contract. And you never invent the percentages: the contract dictates them.

Change-order price calculator

Drag the sliders. Overhead, profit, and bond compound on the running subtotal, in order.

Change-order build-up

Try it yourself

Drag the sliders. Overhead, profit, and bond compound on the running subtotal, in order.

Direct cost50,000
+ Overhead10,000
+ Profit6,000
+ Bond & insurance990
Change order value66,990

The change register — your single source of truth

On a live project, changes arrive faster than they close. The change register is the running list of every potential, pending, and authorised change: its number, description, status, estimated value, time impact, and notice date. It's how the project knows its true forecast cost and completion date at any moment — not the stale numbers in the original contract.

Capture thisSo that later you can…
Change number, description & statusTrack every change through the six lifecycle steps
Estimated value & time impactForecast the true cost and completion date in real time
Notice date & reservation of rightsProve timeliness and keep entitlement alive
Backup documents & correspondenceSupport the price and causation if it's ever questioned

Ten things to remember

  1. A change moves the baseline of scope, time, or price — manage it on paper, deliberately.
  2. Change arrives through two doors — directed (formal) and constructive (forced, undocumented).
  3. A constructive change earns the same entitlement — but you must prove it happened.
  4. Follow the lifecycle — identify → notice → price & time → negotiate → authorise → incorporate.
  5. Notice comes before pricing; authorisation comes before the work.
  6. Miss the notice window and a valid change can be time-barred. When in doubt, give notice.
  7. Price from the bottom up — direct cost, then the contract's compounding markups, never invented percentages.
  8. A change can add cost and time — claim the extension of time and prolongation separately.
  9. The change register holds the project's true forecast cost and completion date.
  10. Contemporaneous records turn a change into a paid change order instead of a disputed claim.

Glossary

Cardinal change
A change so fundamental it falls outside the contract's changes clause.
Change order
The authorised, signed document that adjusts the baseline.
Change register
The running log of all changes and their status, value, and time impact.
Constructive change
Work effectively forced beyond the contract without a formal order.
Contract baseline
The agreed scope, time, and price at signing — the reference every change is measured against.
Directed change
A change formally instructed in writing by the owner or engineer.
Extension of time
Added contract time for an excusable delay, protecting against liquidated damages.
Notice
Timely written notification of a change, required to preserve entitlement.

Check your understanding

1Which best describes a "change" in contract terms?
2A constructive change differs from a directed change because:
3In the change-order lifecycle, when should authorisation happen?
4Direct cost $50,000 with compounding markups (field OH 12%, home-office OH 8%, profit 10%, bond 1.5%). The change-order value is closest to:
5Why does missing the notice window matter?