52R-06Intermediate18 min read

Prospective Time Impact Analysis

A delay has occurred — how many days does the project finish late because of it? A prospective TIA answers by modelling, not estimating: insert a delay fragnet into the current schedule, recalculate the CPM, and measure the net critical movement. Built on AACE 52R-06.

What a Time Impact Analysis is

A delay has occurred (or is about to). The question the contract asks is: how many days does the project finish late because of it? A TIA answers that by modelling — not estimating — the delay's effect on the CPM.

Prospective vs. retrospective

The same fragnet logic can be applied looking forward or backward — and the timing changes the credibility.

Prospective TIARetrospective analysis
WhenAt (or near) the time of the delayAfter the project, looking back
Schedule usedThe current updated schedule's forecastThe as-built record of what happened
QuestionHow much will this delay push completion?How much did delays push completion?
StrengthContemporaneous, no hindsight; ideal for live EOT claimsCaptures what actually occurred, incl. concurrency

The TIA method in five steps

  1. Pick the right schedule — start from the most recent accepted, updated schedule before the delay; its data date should sit just ahead of the delay event.
  2. Build the delay fragnet — model the delay as real activities and logic (duration, predecessors, successors) representing exactly what the delay does to the work.
  3. Insert and recalculate — tie the fragnet into the network at the correct point and re-run the CPM so it recomputes all early/late dates.
  4. Measure the movement — compare the projected completion before and after; the difference is the delay's time impact, the candidate extension of time.
  5. Account for float & concurrency — if the delayed path had float, only the net critical movement counts; check whether any concurrent delay shares responsibility.

Worked example — a single prospective TIA

The current updated schedule forecasts completion on day 200. An owner-directed redesign delays a critical-path activity. The delay fragnet is 15 working days; the affected path carries 4 days of total float.

From fragnet to net extension of time

Worked example
StepValue
Forecast completion (before)day 200
Delay fragnet duration15 days
Total float on the affected path4 days
Net critical impact = 15 − 411 days
Forecast completion (after)day 211
EXTENSION OF TIME = net critical movement (15 − 4 float)= 11 days

The first 4 days of the delay were absorbed by float and cost no time; only the 11 days beyond float moved the completion date. Claim 11 days of EOT — not the full 15. Overstating the impact by ignoring float is a fast way to lose credibility.

TIA impact calculator

Set the delay's duration and the float on the affected path. Only the movement beyond float is a critical impact.

Net extension of time

Try it yourself

Set the delay's duration and the float on the affected path. Only the movement beyond float is a critical impact.

Delay duration15 days
Absorbed by float4 days
New completionday 211
Extension of time11 days

Ten things to remember

  1. A TIA models, it doesn't estimate — it inserts a fragnet and re-runs the CPM.
  2. Prospective TIA is contemporaneous — run on the current schedule, with no hindsight.
  3. Start from the right schedule — the latest accepted update before the delay.
  4. The movement of completion is the time impact — measure before vs after.
  5. Float comes off first — claim only the net critical movement, not the full delay.
  6. Model delays one at a time, in sequence — don't lump them together.
  7. Check for concurrency — a concurrent contractor delay can reduce entitlement.
  8. A non-critical delay moves nothing — duration alone is not impact.
  9. The fragnet must reflect reality — honest durations and logic, or the model is worthless.
  10. Run it contemporaneously — a TIA filed promptly is far stronger than one assembled years later.

Glossary

Concurrency
Two or more delays acting in the same period; can reduce or bar recovery.
Data date
The "as-of" line in a schedule update; a TIA starts from the update just before the delay.
Extension of time
Additional contract time granted for the net critical impact of an excusable delay.
Fragnet
A small network of activities and logic representing a delay or change.
Net critical impact
The delay movement beyond available float — the part that actually extends completion.
Prospective analysis
A forward-looking analysis run at the time of the delay, without hindsight.
Time Impact Analysis
A modelled method that inserts a delay fragnet into the current schedule to forecast its effect on completion.
Total float
The time a path can slip without delaying completion; absorbed before any EOT is due.

Check your understanding

1What does a Time Impact Analysis do?
2Why is a prospective TIA considered credible?
3A 15-day delay hits a path with 4 days of total float. The net extension of time is:
4Forecast completion was day 200; the net critical impact is 11 days. The new completion is:
5If a delay is shorter than the available float, the net impact is: