60R-10Beginner13 min read

Developing the Project Controls Plan

Welcome to Project Controls. A beginner's guide to developing the project controls plan — the document that decides, before work starts, how cost, schedule, and scope will be measured, reported, and kept on track. Built on AACE International RP 60R-10.

What project controls — and the controls plan — are

This opens the Project Controls & EVM track. If estimating and scheduling answer "what will it cost and how long?", project controls answers "are we still on track, and what do we do about it?" — continuously, through execution. And like any discipline, it works only if it's planned: the controls plan is the setup step that makes everything downstream possible.

Why a controls plan matters

  • Sets up consistent measurement — Defines how progress and cost are measured so every report is comparable period to period — no shifting yardsticks.
  • Establishes the structures — Lays out the WBS, code of accounts, and control accounts (the next lessons) that everything is tracked against.
  • Defines cadence & reports — Who reports what, to whom, how often — so trouble surfaces on a predictable schedule, not by surprise.
  • Assigns responsibility — Names who owns each part of the controls process, so nothing falls through the cracks.

What goes into a controls plan

A project controls plan typically defines:

ElementWhat it sets out
StructuresWBS, code of accounts, OBS, control accounts
Baseline approachHow the cost and schedule baselines are set and changed
Progress measurementRules for how % complete / earned value is claimed
Reporting & cadenceReports, KPIs, frequency, and distribution
Change & forecast processHow changes and forecasts (EAC) are handled
Tools & responsibilitiesSoftware, and who owns each controls activity

Using the controls plan

Develop the controls plan at project setup, scaled to the project's size and complexity — a small project needs a light plan, a megaproject a rigorous one. Define the structures, the measurement rules, the cadence, and the responsibilities; get it agreed; and then run it consistently through execution. The discipline isn't writing the plan — it's living by it every reporting period.

Nine things to remember

  1. Project controls measures and manages cost, schedule, and scope against the baseline.
  2. It's a feedback loop: plan → measure → compare → act, every cycle.
  3. The controls plan defines how controls will be performed — set up before execution.
  4. You can't retrofit controls onto a project already underway and in trouble.
  5. It sets up consistent measurement — comparable reports period to period.
  6. It defines structures, baseline, measurement, cadence, change, tools, responsibilities.
  7. Scale the plan to the project — light for small, rigorous for megaprojects.
  8. The discipline is living by the plan — running the loop every period.
  9. Controls unite estimating and scheduling in execution — often via earned value.

Glossary

Baseline
The approved plan that performance is measured against.
Cadence
The reporting frequency and rhythm.
Control account
A point where scope, budget, and responsibility meet (Lesson 3).
Controls plan
The document defining how controls will be performed.
Feedback loop
Plan → measure → compare → act, repeated each cycle.
KPI
Key performance indicator tracked in reports.
Progress measurement
The rules for claiming % complete / earned value.
Project controls
Measuring and managing cost, schedule, and scope vs baseline.

Check your understanding

1What is the main purpose of a project controls plan?
2When is the project controls plan best established?
3A controls plan is most valuable because it makes performance measurement: