84R-13Intermediate15 min read

Planning & Accounting for Adverse Weather

Weather delay is usually excusable but non-compensable — time, not money. Split the weather into normal (your risk) and abnormal excess, then test whether that excess hit the critical path. Built on AACE 84R-13.

Why weather is a special kind of delay

Weather delays are usually excusable but non-compensable: the contractor gets more time, but not more money. Why? Because weather is nobody's fault — the owner didn't cause it, so they shouldn't pay for it; but the contractor shouldn't bear liquidated damages for an act of nature either. So the typical remedy is a time extension only.

Building the weather baseline

To know what's abnormal, you first define "normal" — and you do it before the work, from historical data, not from hindsight. The standard source is long-run climate records (e.g. NOAA in the US) for the project's locale: the typical number of lost days per month from rain, temperature, wind, or other thresholds that actually stop the work in question.

Two pieces make the baseline usable: the anticipated lost days per month (from history), and the work-stopping thresholds (how much rain, or what temperature, genuinely halts this activity — concreting, earthworks, and steel erection have different limits). Bake the anticipated days into the schedule as planned non-work days, and a fair baseline is in place from day one.

The abnormal-weather test, then the critical test

Recovering time for weather is a two-stage test. Clearing the first stage is necessary but not sufficient.

StageQuestionIf "no"…
1 · Abnormal?Did actual adverse days exceed the historical baseline for that month?No excess → no claim
2 · Critical?Did the abnormal excess actually impact critical-path work and delay completion?No critical impact → no extension

Worked example — abnormal excess in one month

Earthworks (a critical-path activity, stopped by rain) ran through a single month. Compare actual lost days to the baseline.

From baseline to excusable days

Worked example
StepValue
Historical baseline rain days (this month)6 days
Actual work-stopping rain days14 days
Abnormal excess = 14 − 68 days
Of which fell on critical-path earthworks8 days
EXCUSABLE EXTENSION = abnormal excess on the critical path= 8 days (time only)

The first 6 rain days were "normal" — the contractor's risk, already in the bid. Only the 8 abnormal days, and only because they hit critical earthworks, support an extension. Note the relief is time, not money: no prolongation cost for ordinary weather delay unless the contract says otherwise.

Abnormal-weather calculator

Set the historical baseline, the actual work-stopping days, and the share that hit the critical path.

Excusable weather days

Try it yourself

Set the historical baseline, the actual work-stopping days, and the share that hit the critical path.

Actual adverse days14
Normal (contractor's risk)6
Abnormal excess8
Excusable extension8 days

Ten things to remember

  1. Weather delay is usually excusable but non-compensable — time, not money.
  2. The contractor owns "normal" weather; the owner risk is the abnormal excess.
  3. Define the baseline up front from historical climate data — not in hindsight.
  4. Set work-stopping thresholds per activity — concreting, earthworks and steel differ.
  5. Bake anticipated weather days into the schedule — good control and claim foundation.
  6. Stage 1 — abnormal? Actual adverse days must exceed the baseline.
  7. Stage 2 — critical? The excess must hit critical-path work to move completion.
  8. Abnormal but non-critical weather earns nothing — float absorbs it.
  9. Keep daily weather records — actual conditions, what stopped, which activity.
  10. Read the contract — some shift weather risk or define abnormal explicitly.

Glossary

Abnormal weather
Adverse weather exceeding the historical baseline for that location and season.
Anticipated lost days
Normal weather days built into the baseline schedule as planned non-work days.
Critical-path test
The requirement that abnormal weather hit critical work to justify an extension.
Excusable delay
A delay that entitles the contractor to a time extension (relief from liquidated damages).
NOAA / climate records
Long-run historical weather data used to set the baseline.
Non-compensable
A delay that earns time but not money — the typical weather outcome.
Weather baseline
The historically expected adverse days per month, defined before the work.
Work-stopping threshold
The condition (e.g. rainfall, temperature) that genuinely halts a given activity.

Check your understanding

1Weather delay is usually:
2Which portion of adverse weather can be excusable?
3Baseline 6 days, actual 14 work-stopping days. The abnormal excess is:
48 abnormal days, all on critical-path earthworks. The excusable extension is:
5Abnormal weather that falls only on non-critical work earns: