38R-06Intermediate14 min read

Documenting the Schedule Basis

A schedule shows dates; the basis explains the why — recording the assumptions, methods, and conditions that made those dates. It's what turns a CPM file into a defensible, reviewable, reproducible plan. Built on AACE 38R-06.

What the schedule basis is

The CPM file is necessary but not sufficient. Two planners given the same scope can produce very different schedules because they made different assumptions — about productivity, sequencing, shifts, resources. The basis captures those choices so the schedule is transparent and reproducible, not a black box.

Why it matters — four jobs it does

  1. Enables review — A reviewer can only judge a schedule if they know its assumptions. "Is 8 days realistic for that pour?" depends on the crew and method the basis records.
  2. Makes it reproducible — Another planner can rebuild or update the schedule consistently because the logic and data behind it are written down.
  3. Protects entitlement — In a delay claim, the documented basis is the reference point for what was planned — and what changed. (This is the scheduling cousin of claims protection, Track 6.)
  4. Aligns stakeholders — It surfaces assumptions for agreement up front — so the owner, contractor, and team commit to the same plan, not different mental versions of it.

What a schedule basis contains

A good basis covers the choices that shaped the dates. Typical contents:

SectionRecords…
Scope & referencesWhat's covered, the WBS, drawings/specs and revisions used
MethodologyHow durations and logic were derived; software and settings
Calendars & workweeksWorking days, shifts, holidays, weather allowances
Productivity & resourcesRates assumed, crews/equipment, key resource limits
Sequencing & strategyExecution approach, phasing, major preferential logic
Constraints & milestonesContractual dates, access, permits, owner-supplied items
Assumptions & exclusionsWhat was assumed and, crucially, what's not covered
Risks & contingencyKnown risks and any schedule contingency/float strategy

When and how to keep it

The basis is written alongside the baseline schedule and issued with it — a schedule submitted without its basis is half a deliverable. Then it's kept alive: each major revision or rebaseline updates the basis to record what assumptions changed and why. A version-controlled basis, paired with each schedule version, is the audit trail that makes the schedule credible from day one to closeout.

Ten things to remember

  1. The schedule basis records why the schedule says what it says — the bars' companion narrative.
  2. The CPM file alone is a black box — assumptions made the dates, and they must be written down.
  3. It's the scheduling cousin of the basis of estimate — same role, applied to time.
  4. Write it as you build — capture assumptions while they're fresh, not after the fact.
  5. It enables review, reproducibility, entitlement protection, and stakeholder alignment.
  6. Cover scope, methodology, calendars, productivity/resources, sequencing, constraints, assumptions, risks.
  7. State exclusions clearly — what the schedule does not assume protects you later.
  8. Issue the basis with the schedule — a schedule without its basis is half a deliverable.
  9. Update it at every rebaseline — version it alongside the schedule for a clean audit trail.
  10. Even a short basis beats none — the discipline matters more than the page count.

Glossary

Assumption
A condition taken as true for planning (e.g. permits by March).
Audit trail
The versioned record of schedules and their bases over time.
Basis of estimate
The cost-side equivalent — the assumptions behind an estimate.
Constraint
An external or contractual date affecting the schedule.
Exclusion
Scope or conditions explicitly not covered by the schedule.
Methodology
How durations and logic were derived; software and settings used.
Rebaseline
Re-establishing the baseline; triggers a basis update.
Schedule basis
The documented assumptions, methods, and conditions behind a schedule.

Check your understanding

1The schedule basis records:
2When should the schedule basis be written?
3Why are exclusions as important as inclusions?
4A schedule submitted without its basis is:
5The schedule basis is the scheduling cousin of: