Original Baseline Schedule Review
Once accepted, the original baseline becomes the yardstick every update, delay analysis, and claim measures against. The baseline review is the gate — a one-time check of completeness, logic health, and realism before anyone signs off. Built on AACE 78R-13.
What the baseline review is
This is the bookend to the update review you met in Lesson 16. That one is recurring — checking each periodic update. This one is the initial acceptance review: a more thorough, one-off examination done when the baseline is first submitted, because everything downstream depends on it being sound.
Why this review is worth the effort
A weak baseline is a problem that compounds. If the accepted baseline has missing scope, broken logic, or buried float, every measurement against it is distorted — and the errors only surface later, usually in the middle of a dispute when they're hardest to fix.
| Baseline flaw | What it causes later |
|---|---|
| Missing scope / activities | "Extra work" claims for work that was always required |
| Open ends / broken logic | An unreliable critical path and false float |
| Excess constraints | A schedule that won't react to delays — masking slip |
| Unrealistic durations | A plan no one can hit — recovery from day one |
The review checklist
A thorough baseline review works through several layers. Many owners apply a DCMA-style metrics check alongside professional judgment:
- Completeness — All contract scope represented; WBS covers the full project; milestones and contractual dates present.
- Logic health — No open ends (dangling activities), minimal/justified lags, no improper SS/FF chains, sensible relationships.
- Constraints — Few hard constraints; each justified. Constraints shouldn't override network logic or hide the true critical path.
- Durations & granularity — Activity durations reasonable (not too long to track); no excessive high-duration activities.
- Critical path & float — A continuous, sensible critical path; float values realistic, not artificially inflated or negative at start.
- Resources & calendars — Calendars realistic (weather, holidays); any resource/cost loading reasonable and not front-loaded.
- Contract compliance — Meets specification requirements: milestones, level of detail, reporting, software, and submission format.
Accept, reject, or accept with comment
The review ends in a decision, documented in a review report. The outcome isn't binary — the realistic options are accept, reject and resubmit, or accept with noted comments to be corrected in the next update. Whatever the call, it should be written down, with findings and the basis for acceptance.
Ten things to remember
- The baseline review is the one-time acceptance check before the schedule becomes the yardstick.
- It's the reviewer's bookend to building the baseline — owner/CM checking the contractor's submission.
- Distinct from the update review (Lesson 16) — that one recurs; this one happens at acceptance.
- A flawed baseline contaminates every later measurement — updates, delay analysis, claims.
- Check completeness, logic health, constraints, durations, critical path, calendars, compliance.
- Open ends and excess constraints are the most common — and most damaging — defects.
- DCMA-style metrics are screens, not verdicts — they flag what to investigate.
- Apply judgment over the numbers — a schedule can pass metrics and still be unrealistic.
- Document the decision — accept, reject and resubmit, or accept with comments.
- Don't accept a schedule you have unresolved concerns about — acceptance carries weight.
Glossary
- Baseline acceptance
- Formally adopting the schedule as the plan of record.
- Baseline review
- The one-time acceptance check of the initial schedule.
- Critical path
- The longest path; must be continuous and sensible.
- DCMA 14-point
- A common set of schedule-health metrics used as screens.
- Front-loading
- Overstating early value/resources — a red flag in cost-loaded baselines.
- Hard constraint
- A fixed date that can override network logic.
- Open end
- An activity missing a predecessor or successor — a logic defect.
- Review report
- The documented findings and acceptance decision.